Construction of 500 5-Storey Housing Units (Maklino Microrayon) 

1992 - 1996 Maloyaroslavets
  • Total Area of 64.222 m2

  • Construction of Asphalt Concrete Pavement Road 

  • 6800 metered Rain-Water and Sewage Pipelines 

  • Potable Water Pipelines

  • Heating Pipelines

  • Low Circuit Lines

  • 2 Transformers with 630 kVA

  • Landscaping

  • Rain-Water Treatment Facility 

Construction of Tyumen Pansionat and Rehabilitation Center with Additional 16 Storey Building Renovation

1992 - 1996 Sochi
  • Construction of 17.000 m2 Facility

  • 5-Star Hotel with 300 beds

  • Mud-Baths and Indoor/Outdoor Swimming Pools 

  • Fitness Center

  • 10” and 17 km of Gas Conveyance Line

  • 35 kVA and 11 km. of Power Transmission Line 

  • Transformer Station

  • Boiler Room to Supply Steam and Hot Water

  • 7000 m. HDPE Pipeline and Waste Water Pumping

  • Installation of 65 cm diameter Fore Piles to Prevent Landslide 

  • Beach Complex

Construction of Aluminum Extrusion Plant and Galvanizing Facility

1992 - 1996 Maloyaroslavets
  • Construction of Production Facility and Administration Building 

  • Installation of Technological Equipment

  • Construction of All Infrastructure Facilities

  • Construction of Residences and All Infrastructure Works

  • Construction of 12.000 m2 Galvanizing Factory 